The opening of bids this week for the first of the two phases saw work offers for the project and its lumber come in much lower than Ocean City Engineer Terry McGean had anticipated.
"The numbers appear to be within the estimate, so it looks like we have a project," McGean told a group of potential builders gathered in a conference room at Town Hall. He met with the bidders moments after council voted 6-1 without discussion in a work session to acknowledge the bids and send them to staff to look over.