Drivers on Route 113 between Snow Hill and Berlin will continue to encounter lane closures during peak travel hours until Memorial Day, with single-lane traffic limited to off-peak hours during the summer as construction crews complete a more than $86 million highway dualization project.
Work on the project, however, could stretch well into next year.
Maryland State Highway Administration Spokesperson Bob Rager, who said Phase 3 of the Route 113 project covers a 4.6-mile stretch of roadway between Massey Branch at the north end and Five Mile Branch Road, provided a progress update on Monday.
“We continue to do a lot of grading, most visibly at the north end near Langmaid Road,” he said. “In a couple of weeks, weather permitting, we’ll put down soil cement, which is a prelude to the first paving operation on the new roadway alignment.”