A $2.5-billion transmission line carrying wind power to the U.S. Southeast is coming -- whether state regulators there like it or not.
On Friday, the U.S. Energy Department used a decade-old statute to clear Clean Line Energy Partners LLC’s 705-mile (1,134-kilometer) power line for construction over any objections from the states involved.
The Energy Department’s approval of the line, proposed to carry 4,000 megawatts of power from the wind-rich Oklahoma panhandle through Arkansas and into Tennessee, marks the first time the 2005 statute has been used to bypass state approval and push through an interstate transmission project.
More
They will clear-cut trees for wires but won't allow a buried pipeline!
ReplyDeleteWABOFM!
Warren Buffet is behind this and stands to profit handsomely
ReplyDeleteThe corporate interests have merged with the government's interests to form a facist tyranny.
ReplyDeleteWelcome to Amerika, where States have no rights (nor citizens).
this is just another reason why we need Trump.
ReplyDeleteI'm guessing that this has something to do with a new 'Google' data center in Clarksville, TN. They are building a 1300 acre site and make the claim that it "..will be powered 100 percent by renewable energy thanks to an arrangement with the Tennessee Valley Authority (TVA)."
ReplyDeleteYour government is BIG business, folks.
Yet our military doesn't have enough weapons or ships to support troops.
ReplyDeleteWind energy is expensive and destroys the local environment. Midwesterners are already suffering from turbine blight and high energy costs...now we will suffer too.
ReplyDeletemeanwhile WV and eastern Kentucky coal mines and towns are turning into ghost towns
ReplyDelete